Question 1
Which of the following statements about critical path analysis is always true?
Tick () one box.
All activity networks have exactly one critical path.
All critical activities have a non-zero float.
The first activity in a critical path has an earliest start time of zero.
A delay on a critical activity may not delay the project.
[1 mark]
Answer