Question 1

The table below shows the lengths, in km, of the roads in a network connecting seven towns, A, B, C, D, E, F and G.

ABCDEFG
Aโ€“24โ€“2235โ€“โ€“
B24โ€“2527โ€“โ€“โ€“
Cโ€“25โ€“33313626
D222733โ€“โ€“42โ€“
E35โ€“31โ€“โ€“3729
Fโ€“โ€“364237โ€“40
Gโ€“โ€“26โ€“2940โ€“
(a)

By adding the arcs from vertex D along with their weights, complete the drawing of the network on Diagram 1 in the answer book.

(2)

Answer
Mark scheme for question 1(a)
(b)

Use Kruskalโ€™s algorithm to find a minimum spanning tree for the network. You should list the arcs in the order that you consider them. In each case, state whether you are adding the arc to your minimum spanning tree.

(3)

Answer
Mark scheme for question 1(b)
(c)

State the weight of the minimum spanning tree.

(1)

Answer
Mark scheme for question 1(c)

Question 2

Figure for question 2
(a)

Explain why each of the dummy activities is required.

(2)

Answer
Mark scheme for question 2(a)
(b)

Complete the table in the answer book to show the immediately preceding activities for each activity.

(2)

Answer
Mark scheme for question 2(b)
(c)(i)

Complete Diagram 1 in the answer book to show the early event times and the late event times.

Answer
Mark scheme for question 2(c)(i)
(c)(ii)

State the minimum completion time for the project.

(c)(iii)

State the critical activities.

(6)

Answer
Mark scheme for question 2(c)(iii)
(d)

Each activity requires one worker. Each worker is able to do any of the activities. Once an activity is started it must be completed without interruption.

On Grid 1 in the answer book, draw a resource histogram to show the number of workers required at each time when each activity begins at its earliest possible start time.

(3)

Answer
Mark scheme for question 2(d)
(e)

Determine whether or not the project can be completed in the minimum possible time using fewer workers than the number indicated by the resource histogram in (d). You must justify your answer with reference to the resource histogram and the completed Diagram 1.

(2)

Answer
Mark scheme for question 2(e)

Question 3

Figure for question 3

Direct roads between five villages, A, B, C, D and E, are shown in Figure 2. The weight on each arc is the time, in minutes, it takes to travel along the corresponding road. The road from D to C is one-way as indicated by the arrow on the corresponding arc.

Floydโ€™s algorithm is to be used to find the complete network of shortest times between the five villages.

(a)

Set up initial time and route matrices.

(2)

Answer
Mark scheme for question 3(a)
(b)

The matrices after two iterations of Floydโ€™s algorithm are shown below.

Time matrix
Route matrix

ABCDEABCDE
Aโ€“84718AABCDB
B8โ€“31510BABCAE
C43โ€“116CABCAE
D7151โ€“1DAACDE
E181061โ€“EBBCDE

Perform the next two iterations of Floydโ€™s algorithm that follow from the tables above. You should show the time and route matrices after each iteration.

(4)

Answer
Mark scheme for question 3(b)
(c)(i)

The final time matrix after completion of Floydโ€™s algorithm is shown below.

Final time matrix

ABCDE
Aโ€“7478
B7โ€“3109
C43โ€“76
D541โ€“1
E6521โ€“

Use the nearest neighbour algorithm, starting at A, to find a Hamiltonian cycle in the complete network of shortest times.

(c)(ii)

Find the time taken for this cycle.

(c)(iii)

Interpret the cycle in terms of the actual villages visited.

(3)

Answer
Mark scheme for question 3(c)(iii)

Question 4

Figure for question 4
(a)

Write down the inequalities that define R.

(2)

Answer
Mark scheme for question 4(a)
(b)

The objective is to maximise P, where P = 3x + y

Obtain the exact value of P at each of the three vertices of R and hence find the optimal vertex, V.

(4)

Answer
Mark scheme for question 4(b)
(c)

The objective is changed to maximise Q, where Q = 3x + ay. Given that a is a constant and the optimal vertex is still V,

find the range of possible values of a.

(4)

Answer
Mark scheme for question 4(c)

Question 5

The nine distinct numbers in the following list are to be packed into bins of size 50

23 17 19 x 24 8 18 10 21

When the first-fit bin packing algorithm is applied to the numbers in the list it results in the following allocation.

Bin 1: 23 17 8

Bin 2: 19 x10

Bin 3: 24 18

Bin 4: 21

(a)

Explain why 13 maths symbol x maths symbol 21

(3)

Answer
Mark scheme for question 5(a)
(b)

The same list of numbers is to be sorted into descending order. A bubble sort, starting at the left-hand end of the list, is to be used to obtain the sorted list. After the first complete pass the list is

23 19 17 24 x 18 10 21 8

Using this information, write down the smallest interval that must contain x, giving your answer as an inequality.

(2)

Answer
Mark scheme for question 5(b)
(c)

When the first-fit decreasing bin packing algorithm is applied to the nine distinct numbers it results in the following allocation.

Bin 1: 24 23

Bin 2: 21 19 10

Bin 3: 18 17 x

Bin 4: 8

Given that only one of the bins is full and that x is an integer,

calculate the value of x. You must give reasons for your answer.

(2)

Answer
Mark scheme for question 5(c)

Question 6

Figure for question 6

[ The total weight of the network is 320 + x + y ]

(a)

State, with justification, whether the graph in Figure 4 is Eulerian, semi-Eulerian or neither.

(2)

Answer
Mark scheme for question 6(a)
(b)

The weights on the arcs in Figure 4 represent distances. The weight on arc EF is x where 12 maths symbol x maths symbol 26 and the weight on arc DG is y where 0 maths symbol y maths symbol 10

An inspection route of minimum length that traverses each arc at least once is found. The inspection route starts and finishes at A and has a length of 409

It is also given that the length of the shortest route from F to G via A is 140

Using appropriate algorithms, find the value of x and the value of y.

(9)

Answer
Mark scheme for question 6(b)

Question 7

A maximisation linear programming problem in x, y and z is to be solved using the two-stage simplex method.

The partially completed initial tableau is shown below.

Basic variablexyzs1s2s3a1a2Value
s11231000045
a13200โ€“10109
a2โ€“10400โ€“1014
Pโ€“2โ€“1โ€“3000000
A
(a)

Using the information in the above tableau, formulate the linear programming problem. State the objective and list the constraints as inequalities.

(4)

Answer
Mark scheme for question 7(a)
(b)

Complete the bottom row of Table 1 in the answer book. You should make your method and working clear.

(2)

Answer
Mark scheme for question 7(b)
(c)(i)
Figure for question 7
Answer
Mark scheme for question 7(c)(i)
(c)(ii)

Write down the basic feasible solution for the second stage.

(3)

Answer
Mark scheme for question 7(c)(ii)
(d)

Taking the most negative number in the profit row to indicate the pivot column, perform one complete iteration of the second stage of the two-stage simplex method, to obtain a new tableau, T. Make your method clear by stating the row operations you use.

(5)

Answer
Mark scheme for question 7(d)
(e)(i)

Explain, using T, whether or not an optimal solution to the original linear programming problem has been found.

Answer
Mark scheme for question 7(e)(i)
(e)(ii)

Write down the value of the objective function.

(e)(iii)

State the values of the basic variables.

(3)

Answer
Mark scheme for question 7(e)(iii)