All papers

Maths · Edexcel 9371 · D1 · Decision Mathematics 1 · January 2011

Edexcel A Level Maths D1 · Decision Mathematics 1 January 2011 question paper 6689

1h 30m 75 marks

Materials

Practise the past exam questions by topic

Edexcel 9371 · Unit 6689

7 questions
Report a problem
What is wrong?

Goes to whoever maintains the question split. No account needed and nothing is published on this page.

Question 1

Figure for question 1

Figure 1 shows a network of roads between eight villages, A, B, C, D, E, F, G and H. The number on each arc gives the length, in miles, of the corresponding road.

(a)

Use Dijkstra’s algorithm to find the shortest distance from A to H.

(5)

(b)

State your shortest route.

(1)

(c)

Write down the shortest route from H to C and state its length.

(2)

Question 2

23 29 11 34 10 14 35 17 The numbers represent the sizes, in megabytes (MB), of eight files. The files are to be stored on 50 MB discs.

(a)

Calculate a lower bound for the number of discs needed to store all eight files.

(2)

(b)

Use the first-fit bin packing algorithm to fit the files onto the discs.

(3)

(c)

Perform a bubble sort on the numbers in the list to sort them into descending order. You need only write down the final result of each pass.

(4)

(d)

Use the first-fit decreasing bin packing algorithm to fit the files onto the discs.

(3)

Question 3

(a)

Use Kruskal’s algorithm to find a minimum spanning tree for the network shown in Figure 2. You should list the arcs in the order in which you consider them. In each case, state whether you are adding the arc to your minimum spanning tree.

(3)

(b)

Starting at A, use Prim’s algorithm to find a minimum spanning tree for the network in Figure 2. You must clearly state the order in which you include the arcs in your tree.

(3)

(c)

Draw a minimum spanning tree for the network in Figure 2 using the vertices given in Diagram 1 of the answer book. State the weight of the minimum spanning tree.

A new spanning tree is required which includes the arcs DI and HG, and which has the lowest possible total weight.

(2)

(d)

Explain which algorithm you would choose to complete the tree, and how the algorithm should be adapted. (You do not need to find the tree.)

(2)

Question 4

Figure for question 4

Six workers, Anthony, Beth, David, Jacob, Kantola and Miri, are to be allocated to six tasks, 1, 2, 3, 4, 5 and 6. Figure 3 shows the possible allocations of the workers, and an initial matching is shown in Figure 4.

(a)

Write down the technical name given to the type of diagram shown in Figure 3.

(1)

(b)

Use the maximum matching algorithm once to find an improved matching. You must state the alternating path you use and your improved matching.

Anthony now agrees to add task 6 to his possible allocations.

(3)

(c)

Starting with your improved matching, use the maximum matching algorithm to obtain a complete matching. You must state the alternating path you use and your complete matching.

(3)

Question 5

Figure for question 5

[The total weight of the network is 31.6 km] Figure 5 models a network of roads. The road markings on these roads are to be renewed. The number on each arc represents the length, in km, of that road. In order to renew the road markings, each road must be traversed at least once.

(a)

Use the route inspection algorithm, starting and finishing at A, to find a suitable route, which should be stated. You must make your method and working clear.

(5)

(b)

State the roads that must be traversed twice and the length of the route.

The machine that will be used to renew the road markings can only be delivered to D. It will start at D, but it may finish at any vertex. Each road must still be traversed at least once.

(3)

(c)

Given that the route is to be minimised, determine where the machine should finish. Give reasons to justify your answer.

(3)

Question 6

Figure for question 6

The graph in Figure 6 is being used to solve a linear programming problem. Two of the constraints have been drawn on the graph and the rejected regions shaded out.

(a)

Write down the constraints shown on the graph.

Two further constraints are

(4)

(b)

Add two lines and shading to Graph 1 in your answer book to represent these constraints. Hence determine the feasible region and label it R.

The objective is to

Question 6, shown as an image

(4)

(c)

Draw a profit line on Graph 1 and use it to find the optimal solution. You must label your profit line clearly.

(3)

Question 7

Figure for question 7

The network in Figure 7 shows the activities that need to be undertaken to complete a maintenance project. The activities are represented by the arcs. The number in brackets on each arc gives the time, in days, to complete the activity. The numbers in circles are the events. Each activity requires one worker. The project is to be completed in the shortest possible time.

(a)

Complete the precedence table for this network in the answer book.

(3)

(b)

Explain why each of the following is necessary.

(b)(i)

The dummy from event 6 to event 7.

(b)(ii)

The dummy from event 8 to event 9.

(3)

(c)

Complete Diagram 2 in the answer book to show the early and the late event times.

(4)

(d)

State the critical activities.

(2)

(e)

Calculate the total float on activity K. You must make the numbers used in your calculation clear.

(2)

(f)

Calculate a lower bound for the number of workers needed to complete the project in the minimum time.

(2)

The paper as printed

Spotted a mistake on this page?Report a problem