Question 1
The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity.
| Activity | Immediate predecessors | Duration (hours) |
| A | – | 2 |
| B | A | 3 |
| C | – | 4 |
| D | C | 2 |
| E | B, C | 2 |
| F | D, E | 3 |
| G | E | 2 |
| H | F, G | 1 |
Model the project using an activity network.
[3]
Determine the minimum project completion time.
[2]
The start of activity C is delayed by 2 hours.
Determine the minimum project completion time with this delay.
[2]