Question 1

This question is about the planar graph shown below.

Figure for question 1
(a)(i)

Apply Kuratowski’s theorem to verify that the graph is planar.

[2]

(a)(ii)

Use Euler’s formula to calculate the number of regions in a planar representation of the

graph.

[1]

(b)(i)

Write down a Hamiltonian cycle for the graph.

[1]

(b)(ii)

By finding a suitable pair of vertices, show that Ore’s theorem cannot be used to prove

that the graph, as shown above, is Hamiltonian.

[2]

(c)(i)

Draw the graph formed by using the contractions AB and CF.

[1]

(c)(ii)

Use Ore’s theorem to show that this contracted graph is Hamiltonian.

[2]

Question 2

Annie and Brett play a two-person, simultaneous play game. The table shows the pay-offs for Annie and Brett in the form (a, b). So, for example, if Annie plays strategy K and Brett plays strategy S, Annie wins 2 points and Brett wins 6 points.

Figure for question 2
(a)(i)

Determine the play-safe strategy for Annie.

[2]

(a)(ii)

Show that the play-safe strategy for Brett is T.

[2]

(b)(i)

If Annie knows that Brett is planning on playing strategy T, which strategy should Annie

play to maximise her points?

[1]

(b)(ii)

If Brett knows that Annie is planning on playing the strategy identified in part (b)(i),

which strategy should Brett play to maximise his points?

[1]

(c)

Show that, for Brett, strategy R is weakly dominated.

[2]

(d)

Using a graphical method, determine the optimal mixed strategy for Brett.

[4]

(e)

Show that the game has no Nash equilibrium points.

[2]

Question 3

An initial simplex tableau is shown below.

PxyzstRHS
1-310000
02011018
0-1230120
(a)

Write down the objective for the problem that is represented by this initial tableau.

[2]

(b)

Variables s and t are slack variables.

Use the final row of the initial tableau to explain what a slack variable is.

[2]

(c)

Carry out one iteration of the simplex algorithm and hence:

• give the pivot column used and the value of the pivot element

• write down the value of P after this iteration

• find the values of x, y and z after this iteration

• describe the effect of the iteration geometrically.

[8]

Question 4

(a)

Show that there are 127 ways to partition a set of 8 distinct elements into two non-empty

subsets.

[3]

(b)

A group of 8 people (A, B, …) have 8 reserved seats (1, 2, …) on a coach. Seat 1 is reserved for person A, seat 2 for person B, and so on. The reserved seats are labelled but the individual people do not know which seat has been reserved for them.

The first 4 people, A, B, C and D, choose their seats at random from the 8 reserved seats.

Determine how many different arrangements there are for the seats chosen by A, B, C and D.

[2]

(c)

The group organiser moves A, B, C and D to their correct seats (A in seat 1, B in seat 2, C in seat 3 and D in seat 4). The other 4 people (E, F, G and H) then choose their seats at random from the remaining 4 reserved seats (5, 6, 7 and 8).

List the 9 derangements of {E, F, G, H}, where none of these four people is in the seat that has

been reserved for them.

[3]

(d)

Suppose, instead, that the 8 people had chosen their seats at random from the 8 reserved seats, without the organiser intervening.

Determine the total number of ways in which the seats can be chosen so that 4 of the people

are in their correct seats and 4 are not in their correct seats.

[2]

Question 5

The manager of a farm shop wants to pave routes on the farm so that, after visiting the shop, customers can visit the animals in fields A, B, C, D and E. The table shows the cost, in £, of making a paved path between each pair of fields. A river means that it is not possible to make a paved path between C and E.

A, BA, CA, DA, EB, CB, DB, EC, DC, ED, E
300500900700200600400500–100
(a)

Determine the minimum cost of connecting the fields.

[2]

(b)(i)

By applying the lower bound algorithm to each vertex in turn, determine a best lower bound for P, the minimum cost of making a circular tour (cycle) of paved paths that visits

each field once.

[4]

(b)(ii)

By applying the nearest neighbour algorithm, starting at each vertex in turn, find a best

upper bound for P. You do not need to attempt any route improvements.

[4]

(b)(iii)

Give the order in which the fields are visited in a circular tour of paved paths that

corresponds to the best upper bound found in part (b)(ii).

[2]

(c)

Give a practical reason why the total cost of paving for the project might be more than the best

upper bound found in part (b)(ii).

[1]

(d)

It becomes possible to use an existing bridge to make a paved route between C and E. Using this bridge, there is a new indirect route from A to D that costs less than £900 to pave.

When this bridge is used, what can be determined about the minimum cost of

(d)(i)

paving the route between C and E

[2]

(d)(ii)

connecting all the fields?

[2]

Question 6

(a)

Suppose that the minimum completion time for the project is 15 minutes.

(a)(i)

By calculating the early event times, determine the range of values for x.

[3]

(a)(ii)

By calculating the late event times, determine which activities must be critical.

[3]

(b)

The table shows the number of workers needed for each activity.

ActivityABCDEFGHIJK
Workers2112n121114

Determine the maximum possible value for n if 5 workers can complete the project in

15 minutes. Explain your reasoning.

[4]

(c)

The duration of activity F is reduced to 1.5 minutes, but only 4 workers are available. The minimum completion time is no longer 15 minutes.

Determine the minimum project completion time in this situation.

[1]

(d)

Find the maximum possible value for x for this minimum project completion time.

[1]

(e)

Find the maximum possible value for n for this minimum project completion time.

[1]