Discrete Mathematics June 2025, Question 4 14 marks
The table shows the activities involved in a project, together with the immediate predecessors and the duration of each activity in hours.
| Activity | Immediate Predecessors | Duration (hours) |
| A | – | 5 |
| B | – | 4 |
| C | A | 3 |
| D | B | 3 |
| E | D | 2 |
| F | B | 5 |
| G | C, E | 2 |
| H | D | 5 |
| I | G | 3 |
| J | C, E, H | 1 |
| K | D, F | 2 |
By constructing an activity network for the project, determine the minimum time in
which the project can be completed.
Reveal mark scheme
State the critical activities.
Reveal mark scheme
Calculate the interfering float for each non-critical activity.
Reveal mark scheme
Each activity requires one worker. When an activity is started it must be completed without interruption.
Use the diagram in the Printed Answer Booklet to determine the minimum number of workers needed to complete the project in the minimum completion time.
Each column in the diagram represents 1 hour. For each worker, write the letter of the activity they are doing in each box, or leave the box blank if the worker is resting for that hour. You
may not need to use all the rows or columns in the table.
Reveal mark scheme
Activity C takes an additional t hours, but all other timings are unchanged.
Determine the range of values of t that result in an increase in the minimum project
completion time.
Reveal mark scheme