Question 1
Complete the table in the Printed Answer Booklet to show the immediate predecessors for
each activity.
[2]
Answer
Carry out a forward pass and a backward pass through the activity network, showing the
early event time and the late event time at each vertex of the network.
[3]
Answer
State the critical activities of the project.
[1]
Answer
Calculate the total float for activity E.
[1]
Answer