AQA A Level Business Studies

Topic questions Decision mathematics Critical path analysis

Critical path analysis

5 questions · 35 marks · about 40 minutes

Critical path analysis questions

TopicCritical path analysis

AQA 7132 Critical path analysis 5 questions

Paper 3: Business 3 June 2025, Question 3 16 marks

VBM’s Operations Director believes that the new factory could be opened in a year.

Do you agree?

Justify your view by using the data in Appendix C and other information provided.

[16]
Reveal mark scheme Mark scheme for question 3

Paper 1: Business 1 June 2024, Question 14 1 mark

Questions 14 and 15 are based on the network below:

Figure for question 14

Referring to the network above, which one of the following statements is true ?

Figure for question 14
[1]
Reveal mark scheme Mark scheme for question 14

Paper 1: Business 1 June 2022, Question 9 1 mark

Statement 1: β€˜In a network diagram, the path with the lowest total float time is the critical path.’

Statement 2: β€˜In a network diagram, at least one activity must have a float time.’

Read statements 1 and 2 and select the correct option from the following options.

Figure for question 9
[1]

Report a problem with a question on this page
What is wrong?

Goes to whoever maintains the question split. No account needed and nothing is published on this page.

Memes

Certified Business Studies memes. Peer-reviewed by nobody.

Laugh now. Cry in the exam hall later. Then come back and do a past paper.

Evaluate both sides
Say β€˜it depends’ and leave
Me on the case study about a bakery
Knowing what profit is
Knowing profit isn't cash flow
Drawing the break-even chart right
Concluding β€˜it depends’ and getting full marks
Business enlightenment, ranked

Mum πŸ’–

how's business studies going?? πŸ₯°

I'm basically a CEO now

then pay your phone bill 😘

πŸ“± Screen time this week Β· Vinted3h 47m

Revenue: zero. Costs: everything

Business starter pack

SWOT analysis of your lifeBreak-even chart in pencilCase study about a juice barThis website
Collect all four